top of page

DRAINAGE

DRAINAGE EXPERIENCE

   Indian Creek Drive from 26 Street to 41 Street Reconstruction - Sea Level Rise Mitigation Project

2017 

-

2019

Client: City of Miami Beach

Financial Project ID: 439228-2-58-01

Project Description: SR A1A/Indian Creek Drive From 25th Street to 41st Street  

Scope of Work: Correct/ Prevent damages from Sea Level Rise Flood Mitigation

REI Responsibilities: Roadway Reconstruction of over 0.9 miles of roadway along with SR A1A/ Indian Creek Drive (raised road 3-ft), the addition of a new 60,000 GPM Pump Station, New Drainage System with a 5200-LF 72-in trunk line, Seawall Replacement, New Signalization, and New Lighting. Harmonization of over 60 adjacent properties and 3 new signalized intersections, development of a Request for Proposal package with conceptual plans and design criteria as part of Phase I of this project.

   SR-9/NW 27th Avenue from South of SR 934/ NW 74th Street to North of SR 932/ NW 103rd Street

2017

-

2019

Client: Miami Dade Expressway

 

Financial Project ID: 429185-3-52-01

 

Project Description: SR 9/ NW 27th Avenue Drainage Reconstruction Project

 

Scope of Work: 2.2 miles of drainage improvements, Roadway Reconstruction, ADA Upgrades, Signal Improvements, Signing & Pavement Markings Improvement

REI Responsibilities: Ribbeck Engineering, Inc. provided engineering design services as a prime consultant for the Drainage Improvements at 23 locations along NW 27th Avenue. Ribbeck handled the design and plans production for the improvements of 2.3 miles including partial roadway reconstruction, signing and pavement markings, and 4 signalized intersections

    SR-925/NW 3rd Court & NW 3rd Avenue from NW 1st Street to NW 8th Street + I-95 Connection Ramps

2017 

-

2019

Client: Miami Dade Expressway

 

Financial Project ID: 429300-4-52-01

 

Project Description: SR 925/ NW 3rd Court & NW 3rd Avenue from NW 1st Street to NW 8th Street RRR improvements project.

 

Scope of Work: Roadway improvements included incidental drainage, partial roadway reconstruction, signing and pavement markings, and 12 signalized intersections.

REI Responsibilities: Ribbeck Engineering, was the prime consultant and managed staff and sub-consultants to ensure cost-efficient and timely improvements, as well as, designing and executing services originally identified, plans production, design, and contract document detailing for the RRR improvements of 1.3 miles along NW 1st Street. 

    FDOT D6 SR 907/Alton Road from 43 Street to Allison Road

2015

-

Pres.

Client: City of Miami Beach

 

Financial Project ID: 430444

 

Project Description: SR 915/ 6th Avenue NE 113 Street Sidewalk and Drainage Improvements

 

Scope of Work: Address drainage needs for both local roads and the State Roadway Facility (LaGorce Island) 

REI Responsibilities: Ribbeck Engineering, Inc. were the drainage engineers on record responsible for the roadway reconstruction of 2-6 miles (raising roadway profile an average of 1.5-feet) along SR 907/ Alton Road, the design of 3 new pump stations in the City of Miami Beach and extensive private property harmonization.

   SR 836/I-95 Interchange Improvements - Design Project Management

2014

-

Pres.

Client: MDX

Financial Project ID: 2516701-22-03

Project Description: 

Scope of Work: The scope of work included developing conceptual plans and RFP, currently provided management and design support. 

REI Responsibilities: Provided Coordination, management and plans review for the MDX portion of the SR 836/I-395/I-95 interchange. Responsibilities during the conceptual phase included the preparation of Design Exceptions and Variations, Typical Section Package, Request for Proposal (RFP) Documents, support in geometric design including horizontal and vertical geometry and preparation of conceptual plans, as well as coordination for Right-of-Way acquisition

   Districtwide Drainage Design & Plans Review Contract - Drainage Consultants
Concrete Wall

2015

-

Pres.

Client: Florida Department of Transportation

 

Financial Project ID: FM 411433-2

 

Project Description: Drainage Design & Plans Review Contract Drainage Support Contract

 

Scope of Work: Design & Review Drainage Plans for 

 

REI Responsibilities: Provided Plans, drainage reports, and bridge hydraulic report review,

Push-button project’s management & execution including preparation of drainage feasibility studies, construction plans and incidental roadway, TCP and PM&S components, and post-design services, Drainage design in-house support, FDOT D6 drainage design guidelines development to supplement statewide drainage criteria, Bridge Hydraulic Report Preparation for riverine and tidal conditions, Specialized drainage design services including pump station design and coastal engineering, Environmental Permitting Support, GIS Support, NPDES Permit Support and Other miscellaneous support including Surveying, Geotechnical, Underwater video inspection, sewer video inspection, Sub-surface utility engineering, Landscape, Lighting, Structural, electrical and mechanical design for pump station incidental work

   FDOT D6 SR A1A Bridge over Haulover Cut – Bridge Deck Drainage Retrofit and Seawall Replacement Scour Analysis

Client: City of Miami Beach

 

Financial Project ID: -

 

Project Description: Ribbeck Engineering Inc. developed construction plans to upgrade bridge deck drainage system and conducted a 2-dimensional tidal hydraulic analysis using Mike-2D software to model tidal hydraulics and estimate scour for seawall replacement.

Scope of Work: Bridge Deck Drainage Retrofit and Seawall Replacement Scour Analysis

REI Responsibilities: Ribbeck Engineering, Inc. provided Structural, Mechanical and Civil Services.

   SR 997/ Krome Avenue from SW 296th to SW 232nd Street – Reconstruction

2017

-

2019

Client: FDOT District 6

 

Financial Project ID:  427369-1

 

Project Description: 

Scope of Work: Reconstruction/ signals for new signalized intersections

REI Responsibilities: Ribbeck Engineering, Inc. provided Structural, Mechanical and Civil Services. Ribbeck Engineering Inc. developed construction plans to upgrade the bridge deck drainage system and conducted a 2-dimensional tidal hydraulic analysis using Mike-2D software to model tidal hydraulics and estimate scour for seawall replacement.

   Dolphin Park & Ride – Civil Site & Drainage Design

2017

-

2018

Client: Miami Dade County Expressway

 

Project Description: Civil Site & Drainage Design

Scope of Work: Preliminary Plans, Pavement Grading, Drainage, RFP Documentation, Permitting

REI Responsibilities: Ribbeck Engineering, Inc. was responsible for the Production of preliminary plans, pavement grading and drainage. Ribbeck handled the RFP Documentation and Permitting.